Is there any relation between the Soma mine disaster & thermal power plants?
Dear
Readers,
We
should keep in mind that the majority of our existing local thermal
power plants do not use high calorie coal from underground mines.
Open-pit lignite coal with a low calorific value is most commonly
used to power existing thermal power plants in generating
electricity. The design for power plants firing imported coal is
completely different. Here, imported coal comes from the nearest sea
port.
Only
at the Çatalağzı- B thermal power plant do we fire byproduct
wastes of the hard coal "water floating enrichment"
process, which has an approx. 3000 kcal/kg LHV (lower heating value).
Here, hard coal is water washed, enriched, and delivered to the steel
industry, and the remaining poor quality byproduct waste is delivered
to the thermal power plant, since it cannot be utilized elsewhere.
You
cannot burn imported coal in a thermal power plant which is designed
to fire poor quality lignite, similarly you cannot fire poor quality
lignite in a thermal power plant that is designed to fire imported
coal. The plant designs are completely different.
The
Soma Eynez underground mine produces high calorie lignite with a
4000-6000 kcal/kg LHV which is then delivered to iron and steel
industries in Aliağa and other nearby industrial zones. The high
quality coal is also used for household heating in the winter. We
have some use of this high quality coal at thermal power plants but
consumption remains very limited.
There
is no direct relationship between the high quality coal of Soma Eynez
and the nearby Soma thermal power plant. The Soma thermal power plant
Unit-B uses poor quality 1500-2200 kcal/kg LHV lignite from open-pit
lignite mines elsewhere in the region, mostly from the Soma Deniş
open-pit coal fields. This low calorie, poor quality lignite cannot
be utilized anywhere other than at the thermal power plants that are
designed to fire this lignite coal.
Elbistan
Kışlaköy and Çöllolar, Soma Deniş, Yeniköy, and Kemerköy
are similar open-pit coal mines that feed the nearby thermal power
plants. On the other hand, at the Çayırhan coal town, there are
newly opened underground quarries that are fully mechanized in their
mining work. In our country there are a few new locations where we
extract high quality coal from underground mine fields in a
mechanized fashion and deliver the fuel to adjacent thermal power
plants.
The
newly commissioned Adularia Yunus Emre Thermal Power Plant, consumes
coal from the mines nearby. Here, the underground mine fields produce
cheaper mine mouth coal prices with full mechanization and qualified
technicians that are employed according to strict safety standards.
Since
the nearby open-pit coal fields are about to be depleted in
Tunçbilek Derin Sahalar (Deep Field), Yatağan Turgut
and Yeniköy Karacahisar, next on the agenda of these operations will
be their further expansion underground in the search for new
mechanized coal investments. Prior to their licensing and investment
incentives, we should encourage full mechanization in their new
investment spending.
However,
each coal field has specific characteristics in that mechanized
underground operation may not be suitable at all times. For
mechanized investment many parameters are to be evaluated. Investors
are to investigate proven reserves, geological structure,
hydrogeological situation, as well as properties of rocks, coal
thickness, depth, width, slope, etc.
In
these new underground mine ventures, we should encourage
fully-mechanized operations if applicable, and try to avoid
labor-intensive coal production. It would be best if we stayed away
from labor-intensive fields that employ shovel production for a
while. We know that each coal field site has its own unique design
and planning. In this regard, making generalizations is not
recommended. The public authorities should impose regulations on
expropriation permits and environmental criteria in order to promote
safer working environments.
In
the Elbistan Çöllolar open-pit low calorie lignite mine fields, we
faced the misfortune of landslides due to ignorance of safe working
standards. This resulted in casualties, whose causes are yet to be
clarified.
The
Yeniköy and Kemerköy open pit coal excavations have depleted the
coal fields, and their natural structures have changed. Here, land
filling, leveling, and planting for agriculture purposes remain
unfinished.
Moreover,
the Yatağan fields produce coal with high levels of radioactivity
and continues to have problems in solving on-site ash dam
accumulation. Other thermal power plants and coal mines are mostly
open pit. With this method, the soil on top of the mine field is
removed and the extracted coal is sent to nearby power plants with
conveyor belts, buckets, etc.
Mechanized
practices are more easily applied in open fields. We do not face the
risk of carbon monoxide poisoning as can be the case with deep
underground labor intensive mining. But here, outdoor operation
problems are different and can include landslides and mine
subsidence. Random and widespread coal fires are another danger.
Different safety measures are necessary in open-pit coal mines.
In
low calorie coal firing thermal power plants, the first ignition in
the boiler combustion chamber is provided by fuel oil burners (no.6).
This design is made to burn the low calorie lignite in bulk
quantities. In these boilers you cannot fire natural gas in lieu of
fuel oil (no.6).
Currently
we have reached an overall 65-GWe installed capacity. However, this
figure is misleading seeing that it includes thermal power plants
that are no longer in operation. For example, Afsin-A, with a 4x340
MWe capacity, is in operation but with one unit only, and this unit
only has a 70% availability. Its other three units do not work.
The
Afsin-B plant has the same four-unit capacity, but here only
two-units are running, the other two-units are defective, they do not
work.
Their
repair has not been completed for the last 2-years. Tunçbilek 1-2-3
does not work. Soma-A does not work. The Hopa plant with a 2x25 MW
capacity also does not work.
The
Kemerköy-Yeniköy thermal power plants have 50% availabilities,
meaning that they are operating at half of their total capacities.
Nonetheless, we incorporate all of these inoperative unit capacities
in our total installed capacity figures. This is not correct. We are
fooling ourselves. Our thermal power plants have completed their
normal lifetimes. They have low efficiencies and low availabilities.
They are unable to run uninterrupted. Serious rehabilitation programs
should be enforced.
In
fact, more precisely, it would be better to remove all of these old
thermal power plants, demolish them, and sell their scraps in a short
amount of time. It is much more efficient, more profitable, and more
feasible to install new thermal power plants which are designed with
new technology, new environmental equipment, bigger dust filters,
better flue gas desulphurization, and bigger ash dams.
We
know that it is difficult to find financing after a privatization
auction. Project finance is always difficult. Investors face project
financing problems prior to taking full ownership of an energy
investment.
Since
the plants are sold with full ownership, there are other investment
options to choose from. In the extreme case, at Kemerköy seaside
plant, you could build a Ro-Ro sea port, a marina-style summertime
vacation resort.
You
could build a new thermal power plant for fire imported coal, or
imported LNG, or investigate if you could build a nuclear power
plant. Plant transmission lines are already available. High-voltage
switchgear facilities are ready. All you have to do is to apply for
investment incentives and licensing in accordance with Energy Market
Law No. 6446. These investment and production licenses are mandatory.
The
investor will need a period of 24-36 months for the receipt of the
necessary licenses. The investor can continue electricity generation
at the old plant to ensure cash inflow until obtaining these
licenses.
We
extend our heartfelt condolences to the families of the victims. Our
hearts go out to those families whose loved ones passed in the Manisa
Soma mine tragedy. Our thoughts continue to be with the people of
Soma County.
Ankara,
29 May, 2014
Haluk
Direskeneli, is a graduate of METU Mechanical Engineering department
(1973). He worked in public and, private enterprises, USA Turkish JV
companies (B&W, CSWI, AEP, Entergy), in fabrication, basic and
detail design, marketing, sales and project management of thermal
power plants. He is currently working as a freelance consultant/
energy analyst with thermal power plants basic/ detail design
software expertise for private engineering companies, investors,
universities and research institutions. He is a member of METU Alumni
and the Chamber of Turkish Mechanical Engineers Energy Working Group.