I'm not rich enough to buy cheap things.
"60-days
non-stop operation" Acceptance Requirement for New Thermal Power
Plants.
Dear
Readers,
Thermal
power plants are designed to operate at least for 30-years. In
practice, they do not exceed 20-year operation. Those exceeding
10-years operation without major overhaul are in limited numbers.
Today, with inexpensive design and poor material
applications, those plants which are supplied and installed by east
Asian contractors merely
pass 2-3 year temporary (trial) acceptance period without major
shutdown.
These
new power plants are designed to poor specs, poor quality norms. They
have insufficient number of spare parts, computer programs for
instrumentation
and control of the combustion are not capable, coal mills and
electrostatic dust precipitator electrodes are eroded fast. Blowers
and fans do not work properly. Electrostatic dust precipitators are
designed so small that they do not meet necessary international
minimum stack emission criteria,
flue gas
desulphurization systems
do not properly work.
Everything
is indexed to the plant design to keep the overall price very cheap.
Such products, designs, thermal power
plants, are not seen in Western Europe, not in North America.
Why do we deserve such poor plants with poor operation? Why don't our
regulatory authorities avoid and interfere such poor applications?
Why don't local companies design, manufacture,
construct new power plants? What is avoiding us?
In
the past decades, Turkish Electricity Authority had famous "60-day
non-stop operation" rule prior to temporary acceptance
certificate of the new thermal power plants. Before two-year
temporary acceptance period, power plant contractors are to prove the
quality of their new plant with "60-day non-stop operation",
so that seller would prove the reliability of the system they were
delivering. Turkish Electricity Authority is unbundled
into 4-different companies, so in the
end the electricity generating company EÜAŞ still has this
requirement in their purchasing
specs but Company has no budget for new power plant investments. Let
us review how to implement "60-day non-stop" operation in
details.
-
New thermal power plant is expected to operate 72-hours non-stop at
full capacity,
-
Within 60-days trial period, plant is expected to operate at minimum
75% capacity,
-
Within 60-days, plant should not stop (trip) more that 5 times in
continuous operation, and those interruptions should not exceed
24-hours.
-
If the thermal power plant can not meet those two conditions within
60-days of trial run, then contractor is to make necessary plant
improvements and restart again.
-
Two-year temporary acceptance period starts after successful
completion of the 60-days nonstop performance test.
In
two year temporary
(trial) period prior to final acceptance of the power plant, plant
should work at least 5000 hours at maximum continuous load without
interruption, and 50% load must be satisfied within 3000 hours of
operation.
Public
thermal power plants are tested in accordance with German DIN-1942,
and DIN-1943 for steam boiler and turbine generator respectively.
These conditions are later modified with new US based EPRI rules and
updated. In local "Electrical Installations Acceptance
Regulation" as released in our Official Gazette in year 1995,
No. 22280, there are many tests, rules and regulations listed for
final acceptance, but "60-days of non-stop operation"
requirement is not covered any more.
Today,
new power plant investments are realized
by private investor companies. They are buying the cheapest plants
and equipment available in the international markets, which are
mostly supplied by east Asian contractors. Suppliers are to present
their supplier credit financing for the projects they are selling in
international markets. Since financing is the key factor of the
contract, the local investor company accepts whatever is delivered.
Electricity generated during test run is delivered to the
national grid free-of-charge, so that private investors prefer to
shorten that test period into 10-30 days, instead of 60-days.
These
de-facto purchase procedures are not correct in the long run. After
barely working for 2-3 years, the new plant plants become
problematic. They can not be operated further without having major
overhaul, expensive and time consuming rehabilitation. They need
renewal of equipment, instrumentations, new spare parts, coal mill
grinders,
e/p electrodes, fans, blowers, new feedwater pumps etc.
"I'm
not rich enough to buy cheap things" is an old English saying.
This is very wise saying that would be found in all languages in a
different form. One should hire independent reliable audit
institutions to monitor and record the plant acceptance test, and
should implement "60-day non-stop operation" rules, prior
to temporary acceptance of the new power plants, thermal, nuclear, or
any other applicable.
All
in all, the plant design with appropriate domestic coal firing
thermal power plants can not be left to the mercy of the foreign
companies, that could escape
the country immediately after delivery. Domestic companies should
lead the power plant contracts with local project financing services.
Oberstdorf, Germany, 30 May 2015
Haluk
Direskeneli, is a graduate of METU Mechanical Engineering department
(1973). He worked in public, private enterprises, USA Turkish JV
companies (B&W, CSWI, AEP), in fabrication, basic and detail
design, marketing, sales and project management of thermal power
plants. He is currently working as freelance consultant/ energy
analyst with thermal power plants basic/ detail design software
expertise for private engineering companies, investors, universities
and research institutions. He is a member of ODTÜ Alumni and Chamber
of Turkish Mechanical Engineers Energy Working Group.
0 Comments:
Post a Comment
<< Home